The Paper Trail: Documentation and Owner Retention from Codes to NFPA 25

The Paper Trail: A Contractor’s Guide to Documentation and Owner Retention from IBC, IFC and NFPA 1 to NFPA 13 and NFPA 25

By Jeffrey M. Hugo, CBO

 

Knowing what documentation must be provided to the owner of a fire protection system for their retention can feel like a moving target. Contractors know NFPA 25, but the International Building Code, the International Fire Code, and NFPA 1 drive what must exist before the first inspection report is generated, and how those permanent records are to be produced and retained. This document distills the model codes and referenced standards into a usable, contractor friendly guide that you can build from in any jurisdiction.

NFPA 25 explains how to inspect, test, and maintain. The adopted fire code makes those requirements enforceable and sets recordkeeping and access rules. When the fire code or NFPA 1 and NFPA 25 differ on retention and availability, the fire code prevails.

From permit to inspection. Required documents and who keeps them

2024 IBC and IFC, NFPA 1 — 2022 NFPA 13 — 2020 NFPA 25

StageWhat is requiredWho produces itWho keeps itAuthority
Design and PermitConstruction documents: sprinkler plans, hydraulic calculations, product data, specifications submitted for approvalFire protection designer or contractorOwner and AHJIBC 107.2.1 and 107.2.2; IFC 901.2 and 901.2.1
Installation and Special InspectionSpecial inspection reports where required verifying anchorage and clearances for drops and sprigs and related MEP supports in Seismic Design Categories C through FSpecial inspector where required and contractorOwner and AHJIBC 1705.13.6; IBC Chapter 17
Acceptance TestingAcceptance test records hydro, flush, main drain, alarm and establish initial records per IFC 901.6.3.1 installer, component types and manufacturers, quantity and location per floor, operation and maintenance manuals kept for the life of the installationContractorOwner baseline record and copy to AHJIFC 901.5; IFC 901.6.3; IFC 901.6.3.1
NFPA 13 DocumentationOwner’s Information Certificate 4.2; Contractor’s Material and Test Certificates aboveground and underground; system signage general and hydraulic data and control valves; as-builts and hydraulic calculations kept with initial recordsContractorOwner for life of systemNFPA 13 4.2; NFPA 13 Chapters 28 and 29; IFC 901.6.3.1
Ongoing Inspection, Testing, and Maintenance (ITM)Perform ITM per NFPA 25 and maintain ITM and system records. IFC jurisdictions retain at least three years on premises or approved location. NFPA 1 jurisdictions retain until useful life is served or as required by law or AHJ and provide to AHJ on requestContractor and OwnerOwner on premises or approved locationIFC 901.6.3; IFC 110.3; NFPA 1 10.2.5 and 10.2.6; NFPA 25 4.3 through 4.3.5
Retention PeriodsMaintain ITM and system records per IFC 901.6.3. Retain at least three years on the premises or other approved location per IFC 110.3 available to the fire code official and copies on request. Where NFPA 1 is adopted keep required records per 10.2.5 and retain until useful life is served or as required by law or AHJ. NFPA 25 4.3.5 retain each record one year after the next occurrence of that type and keep acceptance and initial records for the life of the installationOwnerOwnerIFC 901.6.3; IFC 110.3; IFC 901.6.3.1; NFPA 1 10.2.5 and 10.2.6; NFPA 25 4.3.5
Impairments and ReacceptanceImpairment notifications to the fire department and code official, impairment program tagging at FDC and valves and mitigation or fire watch as required, reacceptance testing and documentation before return to serviceContractor and OwnerOwnerIFC 901.7; IFC 901.6.3; IFC 110.3; NFPA 1 13.3.3.6; NFPA 25 Chapter 15

Who prevails when rules differ

Jurisdictions adopt a fire code that references NFPA 25. The adoption makes NFPA 25 enforceable, and the fire code adds administrative requirements for record creation, retention, and access. When retention timelines or availability rules in NFPA 25 are different from the fire code, the fire code controls. The building code governs plan review and special inspection during construction and does not conflict with NFPA 25’s operations scope.

RequirementIFC 2024NFPA 1 2024NFPA 25 2020Legal Hierarchy
Perform ITM per NFPA 25901.6Chapter 13 water based systems ITM per NFPA 254.3Fire Code governs
Retain Records On Site901.6.3 and 110.3 retain at least three years on premises or approved location and available to the fire code official10.2.5 keep records and 10.2.6 retain until useful life or as required by law or AHJ4.3.5 retain one year after next of that type and life of system for initial and acceptanceFire Code governs
Provide Records to AHJ110.3 and 901.6.310.2.5 and 10.2.3 tests or test reports required by AHJ4.3.4 make records available to AHJFire Code governs
Report Impairments901.713.3.3.6Chapter 15Fire Code governs

Retention clarification

Recordkeeping requirements often overlap between the Fire Code, Building Code, and NFPA 25. The following points clarify how long records must be maintained and which provisions take precedence.

  • Three years is a minimum, not a cap. IFC 110.3 requires at least three years on the premises or an approved location and records must be available to the fire code official. Do not purge everything at three years.
  • Life of installation items remain permanent. Initial records and Operation and Maintenance (O&M) manuals required by IFC 901.6.3.1 are kept for the life of the installation.
  • NFPA 25 can require more than three years. Keep each record one year after the next occurrence of that type, which makes five year items roughly six years. Follow the longer rule when both apply.
  • Who prevails. For operational records, Fire Code retention and availability prevail over NFPA 25 where adopted. For construction-phase special inspections, the Building Code governs that phase and there is no conflict.

Local rules take precedence

This content reflects model codes and referenced standards. Local adoption ordinances often modify administrative chapters that control recordkeeping and retention. When a jurisdiction amends those sections, the local rules prevail over the guidance here and the base model codes.

What locals commonly change:

  • Retention period and location (e.g., keep ITM records on-site for a specified number of years; allow/require off-site or digital custody).
  • Submission requirements (e.g., require uploading acceptance/ITM records to a city portal or filing copies with the fire prevention office).
  • Form and format (e.g., specific AHJ forms for Contractor’s Material & Test Certificates; standardized impairment tags).
  • Approval conditions (e.g., no Temporary Certificate of Occupancy (TCO)/Certificate of Occupancy (CO) until acceptance certificates, O&M manuals, and initial records are received).
  • Third-party compliance (e.g., mandated reporting platforms, private inspection agencies, or UL/FM listing proof submittals).
  • Impairment procedures (e.g., stricter notification, fire watch triggers, or additional reacceptance tests).

Contractor document checklist

Design and permit stage

Construction documents: plans, hydraulic calculations, product data, specifications submitted for approval

Include information needed from the owner’s certificate as applicable to working plans and scope

Installation and special inspection stage

Special inspection reports where required for seismic anchorage and clearances in Seismic Design Categories C through F

Any building official or AHJ required reports associated with any IBC Chapter 17 Special Inspections duties

Acceptance and turnover stage

Acceptance test records: hydrostatic, flushing, main drain, alarm and any pump or trip tests

Contractor’s Material and Test Certificate underground and aboveground

Record drawings and final hydraulic calculations consistent with installation

Establish the initial records file required by IFC 901.6.3.1 including installer information, component inventories by floor, and operation and maintenance manuals

Provide owner with complete acceptance and initial records package

Operations and maintenance stage

Perform ITM per NFPA 25 and maintain ITM records

IFC jurisdictions keep at least three years on the premises or an approved location and make available to the fire code official

NFPA 1 jurisdictions keep until useful life is served or as required by law or AHJ

For five-year events keep records through the next five-year cycle plus one year

Impairments and reacceptance stage

Notify the fire department and code official as required

Tag at the fire department connection (FDC) and valves and implement mitigation or fire watch as required

Complete reacceptance testing and documentation before return to service

File impairment and reacceptance records with the system file and maintain per the adopted fire code

Conclusion

Every NFPA 25 inspection begins years before the first gauge is read. From the moment a sprinkler plan reaches the permit counter, the documentation generated forms the legal and technical record of the system. When contractors build a complete record trail from IBC to IFC and NFPA 1 to NFPA 13 and through NFPA 25 they not only comply with code, they protect the owner, the inspector, and themselves.

About the Author:

Jeffrey M. Hugo, CBO, is Vice President of Codes & Standards, Public Fire Protection, and Training & Education at the National Fire Sprinkler Association (NFSA). A former chief building official and plans examiner, Jeff participates in ICC and NFPA technical committees and guides NFSA’s engagement across major codes and standards. He develops and delivers national training for AHJs, engineers, and contractors, with a focus on practical, field-tested water-based fire protection. 

Contractor's Guide to DocumentationHave code questions? Ask an EOD today or try NFSA’s AI assistant, ChatEOD for an instant answer!